Solutions

Start where the rework is.

Every yard already measures weld rework, fairing hours, coating non-conformance, dock days and schedule slips. Hullira lands on one of those numbers, on one process, with a baseline agreed in writing, and expands when it moves.

6 wedges1 process to startBaseline agreed in writing

run_4b7e19 · agent graph · block B-214 · scenario 10 nodes · 1 approval gate
01 · orchestrator ingest.package ✓ SUCCEEDED 02 · aligna twin.simulate ✓ SUCCEEDED 03 · cut_profile cut.nest ✓ SUCCEEDED 04 · panel_weld weld.sequence ✓ SUCCEEDED 05 · orchestrator approve.human ◆ APPROVAL 06 · quality_anomaly inspect.fuse ✓ SUCCEEDED 07 · fair_form fair.lineheat ✓ SUCCEEDED 08 · blast_coat coat.window ✓ SUCCEEDED 09 · schedule_yard dock.reoptimise ✓ SUCCEEDED 10 · erect_align erect.align ✓ SUCCEEDED

Illustrative scenario: Block B-214 · double-bottom block · panel line PL-2 · dock D1, one block, one approval gate

By outcome

Six wedges, each with a metric the yard already has

The first paid pilot targets one of these. The metric column is what the pilot would be judged on.

Weld quality

Panel lines and block welding cells

Classify defects and predict defect risk at the arc, trim parameters inside the WPS envelope, route the joint to the right check. Metric: weld rework and class-rejected welds against the baseline.

Weldraagent.panel_weld

Distortion and fairing

Repeat block geometries

Predict distortion before welding, pick the sequence on the twin, plan line heating from the scan. Metric: fairing hours and out-of-tolerance blocks against the baseline.

Fairixagent.fair_form

Coating

Ballast tanks and hull areas

Hold the environmental window and film thickness, pause cells when the window drifts, assemble PSPC evidence. Metric: coating non-conformance and re-coat area against the baseline.

Coatiqagent.blast_coat

Erection accuracy

Dock joins

Register both blocks against the twin, predict fit before the lift, guide shimming. Metric: dock hours per join and re-cut or re-fair events at erection.

Alignaagent.erect_align

Dock and schedule

Whole yard

Re-solve dock, crane and berth plans as blocks run early or late, flag schedule risk before it bites. Metric: dock utilisation and schedule slips against the baseline.

Dockosagent.schedule_yard

Outfitting clashes

Open blocks

Check pipe, cable and machinery routes against the as-built block before the steel closes. Metric: clashes found before closing and outfitting rework.

Platformagent.outfit_route
Where it pays

Four loops, four metrics

Hullira is not a dashboard. Each agent closes a loop a yard already measures in rework, fairing hours, coating non-conformance and dock days. The tables show what each loop watches and what it is allowed to move.

Weld quality

Catch the defect at the arc, not at the survey

Weld-pool, seam and bead cameras and the UT and X-ray streams are fused at the yard edge into a live estimate of defect risk per joint. Weldra trims parameters inside the qualified WPS envelope and routes the suspect joint to the right check before the block closes.

  • Porosity, lack of fusion and crack risk scored per joint in real time
  • Parameters moved only inside the WPS and PQR envelope
  • Every joint logged with cited WPS evidence
agent.panel_weld SUCCEEDED
Catch the defect at the arc, not at the survey: signals watched and parameters moved
SignalWatchesMoves
Defect riskWeld-pool and seam cameras, UT, X-rayWire feed, travel speed, heat input inside WPS
Seam sequencePlan from the twinNon-critical seams; class-critical seams under approval
Inspection routingRisk score per jointUT or X-ray queue, hold on the joint
Distortion

Fair the block before it is out of tolerance

A weld-thermal FEA surrogate forecasts how each block moves for a given sequence, heat input, material and geometry. Fairix picks the sequence and back-step pattern before the arc strikes, and plans the line heating from the post-weld scan instead of from a shipwright's eye.

  • Distortion predicted per block before welding starts
  • Weld order and back-step pattern chosen on the twin
  • Line heating planned from the scan, logged with dimensional evidence
agent.fair_form SUCCEEDED
Fair the block before it is out of tolerance: signals watched and parameters moved
SignalWatchesMoves
Predicted distortionFEA surrogate on the twinWeld order, back-step pattern
As-built deviationLaser scan and photogrammetryLine-heating passes, under accuracy-control approval
Block tolerancePer join from the erection planHand-off to Aligna only inside tolerance
Coating

Coat inside the window, prove it for PSPC

Humidity, dew point and steel temperature are read continuously against the coating specification. Coatiq schedules blast and coat to an open window, pauses robotic cells when it drifts, reads dry-film thickness as it goes and assembles the PSPC evidence per area without a clipboard.

  • Environmental window enforced at call time, not checked after the fact
  • Dry-film thickness read per area against the specification
  • PSPC and class evidence assembled automatically
agent.blast_coat SUCCEEDED
Coat inside the window, prove it for PSPC: signals watched and parameters moved
SignalWatchesMoves
Environmental windowHumidity, dew point, steel temperatureBlast and coat timing per area
Surface profileVision after blastingRe-blast flag, cell pause
Film thicknessDry-film gauge readingsStripe coat and recoat inside the specification
Erection and the dock

Land the block on the first lift

Both blocks are scanned and registered against the as-built twin before the crane moves. Aligna predicts the fit, issues shimming guidance, and Dockos re-solves the dock and crane plan as blocks run early or late, so a six-figure-a-day dock is not waiting on a block that will not fit.

  • Fit predicted before the lift from both blocks' point clouds
  • Dock, crane and berth plan re-solved as progress changes
  • Conformance record written per block for the class surveyor
agent.erect_align SUCCEEDED
Land the block on the first lift: signals watched and parameters moved
SignalWatchesMoves
Fit at the jointPoint clouds of both blocksShimming and positioning guidance
Dock and crane planBlock readiness, crane capacity, berthsErection order and slots, under planner approval
Class evidenceWelds, scans, coating readings, approvalsRelease or hold, written for sign-off
Segments

Where yards start

Commercial newbuild, naval and defense, repair and conversion, multi-yard groups and the OEMs that ship into the yard. Most yards pick one process and one wedge, prove the number, then expand.

Commercial newbuildTankers, bulkers, containerships, gas carriers, ferries, offshore

Commercial newbuild

Series vessels with repeat block geometries, where weld rework and fairing hours are already counted. Weldra on the panel line or Fairix on the block type that distorts most.

Naval and defenseProgram schedules, class and naval specs

Naval and defense

Naval shipbuilders under classification-society and naval quality specs with program-office and cyber approvers. Weldra inspection and the Aligna twin, deployed on-prem, with the conformance record from day one.

Repair, conversion and drydockingDock days are the cost

Repair, conversion and drydocking

Yards where the dock is the business and a coating or alignment fault is measured in dock days. Coatiq in the ballast tanks and Dockos on the dock plan.

Multi-yard groups and naval programsOne policy, many yards

Multi-yard groups and naval programs

Groups standardising weld, distortion and schedule models across sites, with the Enterprise tier, fleet-managed yard edge and per-yard private models.

OEMs that ship into the yardWelding robots, coating equipment, scanning, NDT

OEMs that ship into the yard

Welding-robot, CAD/CAM, laser-scan, NDT and coating OEMs embedding Hullira-ready autonomy in what they already sell.

Run timeline · scenario

One scenario run, step by step

Every Hullira run is an ordered, inspectable sequence. This is run_4b7e19 on Block B-214 · double-bottom block · panel line PL-2 · dock D1. Scenario completes in 10 steps with one approval gate. Predicted distortion at the erection joint fell from 4.2 mm to 1.8 mm after a back-step sequence, one porosity precursor on seam S-31 was cleared inside the WPS envelope, the ballast-tank coat ran inside a 3.4 °C dew-point margin, and the block landed at 1.6 mm with its conformance record written.

run_4b7e19 Block B-214 · double-bottom block · panel line PL-2 · dock D1 illustrative scenario SUCCEEDED
  1. 01 ingest.package SUCCEEDED 0.8 s

    Yard Orchestrator · Pulled the work package for B-214 from the yard MES: 46 plates, 212 seams under WPS-117, erection tolerance 2 mm at the D1 joint, PSPC-grade ballast-tank coating, erection slot on D1 in the dock plan. Locked the qualified WPS envelope and the class scope.

  2. 02 twin.simulate SUCCEEDED 1 m 12 s

    Ship Twin · Simulated 18 candidate weld sequences on the as-built twin with the weld-thermal surrogate, ranked on predicted distortion at the erection joint, crane reach on D1 and shift takt. Standing sequence predicts 4.2 mm; candidate #6 predicts 1.8 mm.

  3. 03 cut.nest SUCCEEDED 3 m 40 s

    Cut-and-Profile · Released the nest for 46 plates on CL-1 with the fit-up gaps candidate #6 assumes. As-cut geometry logged per plate and handed to the panel line; material yield 91.4% against the nest plan.

  4. 04 weld.sequence SUCCEEDED 2 m 05 s

    Panel-and-Weld · Loaded the back-step sequence for the non-critical seams on PL-2 and set heat input and travel speed inside WPS-117. Weld-pool and seam cameras streaming on 12 channels.

  5. 05 approve.human APPROVAL 58 s

    Yard Orchestrator · Candidate #6 also re-orders two class-critical butt seams, S-31 and S-32. Sequence changes on class-critical seams stay with a human, so the step was held for the shift welding engineer and approved at 06:12:44.

  6. 06 inspect.fuse SUCCEEDED continuous

    Quality-and-Anomaly · Twelve weld cameras and the UT station fused at the yard edge. One porosity precursor on S-31 at 06:41 flagged and cleared by a 4% wire-feed trim inside the WPS-117 envelope; the joint was routed to UT and passed.

  7. 07 fair.lineheat SUCCEEDED 4 m 30 s

    Fair-and-Form · Post-weld scan registered against the twin: 2.1 mm at the erection joint. Two line-heating passes planned on the inner bottom and executed by the fairing crew; re-scan read 1.8 mm, inside the 2 mm tolerance.

  8. 08 coat.window SUCCEEDED continuous

    Blast-and-Coat · Ballast-tank blast and first coat scheduled to a window with steel temperature 3.4 °C above dew point. Dry-film thickness read 312 µm against a 280 µm minimum on the stripe coats; PSPC evidence assembled per area.

  9. 09 dock.reoptimise SUCCEEDED 41 s

    Schedule-and-Yard · Re-solved the D1 dock and crane plan with B-214 ready 6 hours early and a neighbouring block late: erection slot pulled forward one shift, crane G2 reassigned, no berth conflict. Planner approved the revised plan.

  10. 10 erect.align SUCCEEDED 1 h 48 m

    Erect-and-Align · Both blocks scanned on D1 and registered against the twin; fit predicted at 1.6 mm. Shimming guidance issued to the erection crew, block landed and welded out, final scan 1.6 mm. Conformance record written: welds, scans, coating readings, approvals and class evidence for B-214.

Who it is for

Built for the people who run the yard

We have no customer quotes to show yet and will not invent any. These are the three roles in a yard we build for, and the problems they bring to the first meeting.

Yard or Production Director

Owns launch dates, the dock schedule, labour, rework and cost.

What this person is dealing with today

  • Paper travelers, manual measurement and periodic inspection that let weld quality, distortion and schedule drift
  • Dock, crane and berth slips cascading across the order book
  • A severe, retiring welder and fitter shortage against order books stretching past 2030

Welding or Accuracy-Control Engineer

Owns weld procedures, distortion and fairing strategy, dimensional accuracy and class approval.

What this person is dealing with today

  • Weld-parameter and sequence drift driving class-rejected welds, distortion and rework
  • Hull-fairing and erection dimensional error costing days of dock time per block
  • Cutting, welding, fairing, coating and erection siloed and reactive across the yard

Quality, HSE and Class-Compliance Lead

Owns weld, coating and dimensional quality, non-conformance, PSPC and classification-society and naval-program traceability.

What this person is dealing with today

  • Coating and surface-prep faults driving premature failure and warranty claims
  • Patchy traceability for class and PSPC audits
  • Outfitting clashes discovered after steel is closed, forcing cut-and-reweld rework
Autonomy

Four levels, set per agent and per tag

A yard does not go from paper travelers to unattended welding in one step. Hullira makes the level explicit, auditable and reversible at any time. The first release runs shadow mode, then assist mode, then supervised control on low-risk actions. Class-critical seam changes, lift plans and block release stay with named people.

Autonomy levels and the human role at each
LevelWhat the agent doesWhat the human doesWhere it sits in a pilot
L1 · ShadowReads weld, scan, NDT, coating, robot, crane and MES signals; predicts and recommends; writes nothingRuns the process as today; compares predictions to NDT and surveyor outcomesShadow mode; the baseline is measured from the yard's own records
L2 · AssistProposes weld, fairing, coating, routing and schedule moves with evidence, confidence, envelope and rollback pathApproves each action in the review consoleAssist mode, the remainder of the pilot
L3 · Supervised controlExecutes pre-approved low-risk actions: inspection routing, coating pauses when a window drifts, weld parameters inside the WPS envelope, robot path variants tested in simulationApproves class-critical seam changes, lift plans and block releaseGraduated autonomy, after audited accuracy and ROI
L4 · BoundedSupervised work sequencing and weld adaptation for qualified block types, across processes and yardsSets the envelope; reviews the shift record and the evaluation resultsPlanned; after class, yard and insurer acceptance is earned
Pricing

Priced per process, per yard, per group

Land on one workflow with a measured baseline. Expand by process, yard, group site and autonomy level. Outcome components are available on rework, dock time and schedule value. Annual prepay carries a 15 to 20% discount.

Billing period
Process $12,000 per production process or area / month · billed monthly

Weld, fairing or coating control, or weld-inspection AI, for one process. For yards validating ROI on the wedge.

  • One process or area, one agent module
  • Yard-edge inference node included
  • Robot, instrument and MES reads, guarded writes
  • Run log, audit trail, block genealogy
  • Business-hours support
Start a pilot
Enterprise Custom land $700k to $10M ACV

Multi-yard groups and naval programs standardising on Hullira, with custom weld, distortion and schedule models.

  • Multi-yard and program fleet management
  • Custom weld, distortion and schedule models
  • Yard-edge fleet with on-prem option
  • Group autonomy policy and approval chains
  • SLAs, SSO and RBAC, dedicated engineer
Contact us
FAQ

Straight answers

The questions production directors, welding engineers and class-compliance leads ask in the first meeting.

Yes, but only within an explicit tag allow-list with per-tag rate and magnitude limits, inside the qualified WPS, coating, dimensional and schedule constraints, and only at the autonomy level your yard has set. Design partners start in shadow mode, where Hullira writes nothing. Class-critical seam changes, lift plans and block release stay with named people.

Get started

Name the process that costs you the most

Start with one welding, fairing, coating or erection process and one measurable baseline. A paid pilot on weld inspection, distortion control or coating assurance shows the number before you commit further.